Every morning, roughly 200 staff converge on Deer Valley’s east flank, placing ending touches on the most important ski growth in US historical past. It’s onerous to imagine Alterra Mountain Firm and Extell Growth Firm unveiled their partnership to convey the Mayflower challenge beneath Deer Valley’s model lower than two years in the past. By December, a 3 mile gondola, two six packs and 7 quad chairs might be prepared for skiers, finishing nearly all of the Expanded Excellence imaginative and prescient. After a restricted preview final season, Deer Valley’s footprint will greater than double this winter to 4,300 acres and 31 lifts. The growth spans 2,850 ft of vertical reduction, with the gondola alone rocketing 2,570 ft skyward in 14.5 minutes.
Deer Valley Senior Director of Mountain Operations Garrett Lang and Alterra Senior Supervisor of Building Pete McKinnon graciously took time to indicate me round this week. I’ve by no means seen so many lifts at each stage of building from concrete to rope pulling. Past lifts, some 1,250 fastened snow weapons, a ridgetop snowmaking pond, a number of pumphouses and a upkeep facility are additionally nearing completion. It appears like Deer Valley’s constructing a metropolis’s value of infrastructure on the aspect of a mountain. In fact each fan gun, each elevate tower and each terminal sport Deer Valley inexperienced.
The one strategy to full such an bold challenge in three building seasons was to divide and conquer. Whereas Doppelmayr equipped all of the lifts, they’re solely assembling a few of them. Huge-D Building crafted quite a few foundations whereas already on web site engaged on buildings. Highlander Ski Carry Companies & Building tackled roughly half the chairlift installations from begin to end. Doppelmayr introduced in elevate building consultants from throughout, together with Canada and Europe.

Most readers know Deer Valley launched the six place Keetley Specific and two close by quad chairs final season. Whereas Keetley’s beautiful, she represents a small portion of the general challenge. Inside that preliminary footprint, Layton Building continues work this summer time to finish a parking constructing for Keetley’s 102 bubble chairs. Proper subsequent to the highest of Keetley sits the highest of Galena Specific, considered one of two removable quads completed and commissioned final spring. The second is Pioche Specific, connecting the underside of Aurora to the northernmost summit within the 2,274 acre growth.
The smallest elevate beneath building is Neptune Specific, set to load under Pioche Village and high out subsequent to Pioche Specific. This is without doubt one of the two machines Highlander’s putting in this summer time on high of a number of final yr. The Highlander crew was finishing the highest drive terminal this week with the underside to comply with.


The flagship East Village Specific gondola will run all the way in which to Park Peak. A behemoth of a mid-station sits on Huge Dutch Peak, the place the elevate’s two sections join at an angle. Every section options its personal direct drive and a Fatzer Performa-DT haul rope with cabins capable of change between traces. All three stations and many of the 40 towers have been put in earlier this summer time. Fatzer subsidiary Rigging Specialties labored to tug ropes this week with the decrease line already on most towers. The higher rope, being put in now, will go over a number of extraordinarily tall towers and journey downhill at a number of factors alongside the road.
142 Omega V cabins are set to start arriving from Switzerland subsequent week. Just like Steamboat’s Wild Blue Gondola, they’ll characteristic particular person logoed seats. At Deer Valley, they’ll be heated. Huge-D Building is piecing collectively the gondola’s parking facility, positioned beneath the long run Park Peak lodge. Lodge companies received’t be prepared for this winter however the first ground parking system ought to be. It is going to be absolutely automated and the plan is to park cabins nightly. The Park Peak complicated is designed for a doable third gondola section all the way down to Silver Lake Village.
For now the D-Line Pinyon Specific will join historic Deer Valley to new terrain. It’ll load between Bald and Flagstaff mountains, lifting six company at a time to Park Peak with elective bubble. Pinyon will intently mimic Keetley Specific, although with longer terminals for in-station parking. 9 of 11 towers and the highest station are full with the underside station going up now.


The final two items of the chairlift community are what the event crew name 6A and 6B, initially deliberate as one elevate with an intermediate station. Now dubbed Vulcan Specific and Revelator Specific, these steep UNI-G quads will service a number of the greatest fall line snowboarding in Utah. Revelator will cross beneath the gondola and attain the excessive level of the growth – 9,370 ft. Revelator’s backside terminal is in with concrete nearly full and towers to comply with in early September. “We’re nearly out of the concrete enterprise,” McKinnon famous.

Highlander is engaged on 6A/Vulcan, the decrease elevate that can present egress from a big bowl that makes up the southern boundary for now. From the Vulcan Specific unload, skiers will head proper towards the East Village or left to proceed up Park Peak through Revelator.


Final however not least are three SunKid conveyors to be located within the East Village. These type the start of a ski college development from carpet to newbie chairlift to Keetley Specific or the gondola. Each elevate within the growth will service at the very least one inexperienced route, together with a 4.85 mile snake named Inexperienced Monster.
Deer Valley notes 1,200 day skier parking spots might be prepared this season within the East Village, up from 500 final winter. A everlasting skier companies constructing received’t be however company can journey a tram to non permanent services by the gondola (the journey might be shorter than final winter’s to Keetley.) For vacation spot guests, the Grand Hyatt Deer Valley is already open with a 4 Seasons and Cover by Hilton beneath building.

The Hail Peak Upkeep Facility features a 10,000 gallon per minute pumphouse and area for automobile upkeep with three cat bays. A ten million gallon storage pond is being excavated close to Park Peak, fed from the Jordanelle Reservoir under. The snowmaking system will embody central air traces, which means no onboard compressors wanted for 150 TechnoAlpin fan weapons. The overwhelming majority of the system’s 1,100 HKD stick weapons might be absolutely automated.

This season received’t mark the top for Alterra and Extell’s building groups. Deer Valley not too long ago introduced a further UNI-G removable quad to open for 2026-27 on Hail Peak, serving seven runs and offering direct elevate entry from the day skier car parking zone. Even as soon as that elevate is accomplished, company needing leases or classes can go for a tram journey by way of a brand new tunnel to the village. There might be escalators.

A number of extra lifts stay within the grasp plan with no set timelines for building. Attainable future initiatives embody a quad on the bottom of Bald Mountain, an extended Crown Level elevate beginning under Keetley Level and a lapable six pack on Huge Dutch Peak. Past lies South Peak, an knowledgeable’s paradise with two doable chairlift alignments. Resort leaders are taking a wait and see strategy, watching how skiers stream the following few seasons. With almost 100 new trails this winter, it’s going to be awhile earlier than Deer Valley wants extra terrain.
Because of Carry Weblog reader and pilot Auston C. for flying me over the growth and to the Deer Valley crew for internet hosting me.